Project

1 unit of 2 MW to Hydro power station

1 unit of 2 MW to Hydro power station Ganji Skardu

About The Project

1 unit of 2 MW to Hydro power station Ganji Skardu

Supply, Installation, Commissioning & Test running of 1 unit of 2 MW to Hydro power station Ganji Skardu

Detail Project

Installed Capacity

The project involved the addition of a significant new unit to the power station:

  • Number of Units: 1

  • Unit Capacity: 2 MW(Megawatts)

  • Total Capacity Addition: 2 MW

This expansion contributes essential electricity to the local grid, supporting the energy needs of the Ganji area and surrounding communities in Skardu.

Scope of Work

The contractor, Mushtaq Ali Government Contractor Gilgit Baltistan, was responsible for the following comprehensive activities related to the 2 MW unit:

  1. Supply: Procurement and delivery of all necessary mechanical, electrical, and civil components for the 2 MW hydropower unit.

  2. Installation: Complete physical installation of the turbine, generator, control systems, and associated balance of plant equipment.

  3. Commissioning: Detailed functional testing of all installed equipment and systems to ensure they operate according to design specifications and safety standards.

  4. Test Running: A sustained period of operational performance testing to confirm the unit’s reliability and output capacity prior to handover.

Project

Project in capture